Elk Creek
____ - 1913
March 14, 1913: "Sealed bids will be received by the County Court of Douglas County, Oregon, up to 12 o'clock M. of the 2nd day of April, 1913, for the construction of the following bridge.
The Hancock Bridge: Two 126 feet steel spans, Pratt truss design, approximately 190 feet of framed wood trestle approaches, six steel tubular piers, approximate height 36 feet; The bid to include the removal of the old structure now in use." (Roseburg Review)
The Hancock Bridge: Two 126 feet steel spans, Pratt truss design, approximately 190 feet of framed wood trestle approaches, six steel tubular piers, approximate height 36 feet; The bid to include the removal of the old structure now in use." (Roseburg Review)
March 14, 1913: "Before adjournment the first of the week, the county commissioners authorized the construction of three new bridges as follows:
Hancock bridge near Drain, to cost $10,000." (The Sutherlin Sun)