August 25, 1899: "In the matter of an advance payment to Morris & Olds on their contract for building the Rock creek bridge. The board being fully advised in the matter it is ordered that the sum of $100 be paid to Morris & Olds as an advance payment to be taken from the contract price for building said road." (Oregon City Courier=Herald)
August 25, 1899: "In the matter of the error in the survey of the Rock creek bridge site. It appearing to the boiard that there has been an error made in the survey of said bridge site, and said bridge will have to be ----feet longer than the contract calls for, it is ordered by the board that the contractors be allowed an additional sum of $88.45 over and above the contract price to compensate them for building said additional length to said bridge." (Oregon City Courier=Herald)
October 20, 1899: "In the matter of accepting the Rock Creek bridge from the contractors, Morris & Olds. The board having examined and accepted said bridge and being fully advised, it is ordered that said bridge in all respects be accepted and approved and the Clerk is hereby ordered to issue a warrant in favor of said Morris & Olds for $948.50, the contract price of said bridge, plus $88.45 extra for mistake made in length of bridge when survey of bridge site was made, making a total of $1036.95 less one hundred dollars already advanced to contractors." (Oregon City Courier=Herald)
April 28, 1905: "In the matter of repairs to bridge across Butte creek at Monitor and the Rock Creek bridge, ordered that the Bagby Lumber Company be notified to repair the piers to said bridges and remove drift from around same." (Oregon City Courier)
July 18, 1919: "On Tuesday the east Clackamas road was closed for ten days, for paving near Rock Creek bridge and raising the bridge." (Oregon City Enterprise)